Development of design and cost-estimate documents for drinking water supply in Agarak settlement, Kapan community, Syunik Marz, RA
The developed detailed design envisaged the capture of the “Chrchr Verin” water spring, the renovation of the water intake structure of the “Chrchr Nerkin” spring and the construction of a valve junction adjacent to it, as well as the construction of a 733m long water pipeline between the springs from 50mm polyethylene pipes.
It was also planned to implement a 20mm diameter steel pipeline from the “Chrchr Verin” spring to the existing drinking bowl for watering․